625m OFC Maintenance interdepartment

Client: UNAAB (University of Agriculture, Abeokuta)Sector: EducationLocation: Osiele Abeokuta, Ogun stateCompleted: 2010Duration: 12 days Performed critical maintenance on 625m of interdepartmental optical fiber network, enhancing campus connectivity and academic operations.

BAGCO PLC Fiber Maintenance

Client: BAGCO PLCSector: ManufacturingLocation: Eric Moore Rd, Surulere, LagosCompleted: 2009Duration: 3 days Conducted maintenance operations on 850m of optical fiber infrastructure, ensuring continued network reliability for manufacturing operations.

1.2km OFC Fiber stringing for PHCN Telemetry/scada

Client: Phase3 Telecom LtdSector: TelecommunicationLocation: Akangba 330kv Station, SurulereCompleted: 2011Duration: 5 days Rapid deployment of 1.2km optical fiber stringing for PHCN’s Telemetry/SCADA system, enabling improved power grid monitoring and control.

4.8km OFC turnkey solution for MTN Nigeria

MTN Nigeria OFC Turnkey Solution – NFE 5 Client: Barleyfield Nig LtdSector: TelecommunicationLocation: Victoria Island, LagosCompleted: 2011/12Duration: 3 months Executed a 4.8km optical fiber cable turnkey solution for MTN Nigeria in Victoria Island, strengthening network capabilities in this key business district.

2.5/16.5/6km OFC turnkey solution for MTN Nigeria

Client: Barleyfield Nig LtdSector: TelecommunicationLocation: Onitsha/Asaba/Vandez, Anambra stateCompleted: 2010Duration: 7 months Successfully implemented a multi-segment optical fiber cable solution covering 2.5/16.5/6km for MTN Nigeria, enhancing network infrastructure across multiple locations in Anambra state.

Building of Ethernet LAN for Lets Go Bowling

Client: Sheperdhill Ltd Sector: Estate Project Development Location: The Palms shopping mall, Lekki Date: 2009 Duration: 3 months Project Details: In 2009, we constructed an Ethernet LAN for Lets Go Bowling at The Palms shopping mall in Lekki. This project, completed within three months, provided the network infrastructure for the bowling alley.